2023 Sealcoat Project

Overview

Annually, the Township completes a sealcoat project to extend the life of its streets. It is estimated that a sealcoat application can extend the life of pavement from three to six years. Sealcoating is the application of asphalt emulsion followed immediately with an aggregate cover. Excess aggregate is then swept up a few days later. 

This year's project is scheduled tbd, weather permitting, and the entire project is scheduled to start July 20th (weather permitting).  The sealcoating process moves along quite rapidly so any delays in travel should be kept to a minimum.

Your street access may be limited during the asphalt emulsion application until the aggregate cover is applied. After the street is open to traffic, please use extreme caution when stopping, starting, or backing out of your driveway. Turning the steering wheel while stopped will cause damage to the new surface during its curing stage. 

Project Schedule

  1. Town Board accepted bids and awarded contract to Allied Blacktopping Company March 6, 2023.
  2. Sealcoating will take place starting July 20 weather permitting.
  3. Cracksealing was awarded to MP Asphalt Maintenance on March 6, 2023. The cracksealing will begin as soon as the snow melt is done.
  4. Public Works staff will complete mill and patching beginning in late April thru May 2023.

2023 Sealcoat Maps